This week, a contractor has been on-site completing asbestos abatement within the building located at 3200 S. Kedzie (Azteca Mall). The abatement is on schedule to be completed by the middle part of next week.

Next week, a contractor will be completing a water disconnection at S. Kedzie on the West side of the street. This will disconnect the water service to the building at 3200 S. Kedzie. One of the two southbound traffic lanes may be partially obstructed during this week but the crew will work to limit any inconvenience. 

We anticipate demolition permits will be issued by the City of Chicago within the next two weeks and demolition work will commence promptly thereafter. The work will begin on the 3 structures and a concrete wall at 3345 W. 31st Street (Action Iron). 


Daily air quality monitoring will be conducted during the demolition work and the reports will be posted on this website.

Please call our hotline with any questions or concerns. 773-484-1049.