• Took down a 200,000 SF former industrial building, a 10,000 SF brick building, a 2,500 SF brick building, an 11,000 SF brick building, and approximately 1,300 linear feet of concrete wall.
  • The work took 41 working days. The first day of work was 1/25/22 and the final day was 4/15/22. There was a 1-month gap between phase 1 and phase 2 of demo.
  • There were 131 truckloads of scrap and 124 truckloads of demolition debris removed from the property.
  • Air Quality Monitoring took place at all times during demo activities. The reports can be found on the project website. The contractor was effective in controlling and suppressing dust throughout the project.

A community meeting is being held on April 19th at 6 PM to provide an overview and recap of the project. A notice for that event is included here.