December 16, 2025 Phase One of the Environmental Cleanup for Focal Point Community Campus Completed

Revitalization of the Land and Community Continues to Progress for the Future Mixed-Use Campus Chicago Southwest Development Corporation (CSDC) has completed Phase One of the environmental cleanup for the future home of Saint Anthony Hospital on the Focal Point Community Campus, at the corner of 31st St. and Kedzie Ave. […]

Read More

October 2, 2025 Environmental Remediation Update

The sewer installation on 31st Street was successfully completed without any traffic incidents. The steel plates that were in place have been removed just in time for the Mexican Independence Day Parade in Little Village. The trench that was restored with concrete will be milled and resurfaced with asphalt in […]

Read More

August 22, 2025 Environmental Remediation Update

Crews at the property are performing extensive excavation work, breaking foundation walls, breaking concrete, and soil haul off at the property. Starting on Monday 8/25, and scheduled to complete on 8/29, crews will be performing work on 31st Street, to make a stormwater connection. The plans for street work were communicated […]

Read More

July 28, 2025 Environmental Remediation Update

Crews at the property continue to make great progress on the environmental remediation project at the southwest corner of W. 31st and S. Kedzie Avenue, as they continue excavation work and soil haul off. They continue to prioritize dust control, traffic maintenance, and air quality monitoring throughout the course of […]

Read More

July 2, 2025 Environmental Cleanup Project Update

Cleanup work commenced on 6/23. Crews have completed site clearing, surveying work, fence screening installation, and have installed their trailer and security cameras. Crews have also started additional required soil samples, concrete loading and haul out, watering and dust control, air quality monitoring, and traffic controls. Over the next week, […]

Read More

Community Meeting Held on June 16, 2025

Environmental Project Updates: The environmental cleanup work will be conducted in phases and will commence on the former Washburne Trade School parcel (the northern-most 11 acres on the Focal Point site. The proposed remedial actions include: (1) The utilization of engineered barriers consisting of concrete, asphalt, and building foundations planned […]

Read More