November 18, 2021 – EPA Cleanup Grant Program

November 18, 2021 – Chicago Southwest Development Corporation and Saint Anthony Hospital hosted a community meeting at St. Agnus of Bohemia Catholic Church to update the community on the Focal Point Community Campus. You can find a recording of the meeting at the following link: https://www.facebook.com/FocalPointChicago/videos/397895688757038/Download Presentation Here

Read More

Project Update #3 – November 1, 2021

The water disconnection at 3200 S. Kedzie was completed on October 29th. The section or road that was cut into will be repaved. Asbestos abatement was completed on October 28th within a portion of the buildings located at the same address. CSDC is awaiting demolition permit issuance from the City of Chicago and will begin […]

Read More

Project Update #2 – October 26, 2021

Asbestos abatement is expected to be completed this Thursday within the building located at 3200 S. Kedzie (Azteca Mall). A contractor is scheduled to complete a water disconnection at S. Kedzie on the West side of the street this Thursday and Friday (10/28 and 10/29), but this scheduling is dependent on the Department […]

Read More

Project Update #1 – October 19, 2021

This week, a contractor has been on-site completing asbestos abatement within the building located at 3200 S. Kedzie (Azteca Mall). The abatement is on schedule to be completed by the middle part of next week. Next week, a contractor will be completing a water disconnection at S. Kedzie on the […]

Read More

September 29, 2021 – Demolition Project Community Meeting

Chicago Southwest Development Corporation (CSDC) hosted a virtual community meeting via Zoom, with simultaneous professional Spanish translation. There were roughly 60 people in attendance. CSDC posted notice on its social media pages, emailed notice to an extensive community stakeholder list, emailed notice to people who had attended prior community meetings, and went door-to-door in the community to flyer for the event.

Read More