Monday, May 2, 2022
The demolition contractor is back at the property this week to take down a remaining concrete wall. The work should take 3-4 days, and air quality monitoring will be taking place at all times during
Read More -
April 18, 2022 – All buildings are down and the demolition work is complete. Photos are included here for your reference.
Took down a 200,000 SF former industrial building, a 10,000 SF brick building, a 2,500 SF brick building, an 11,000 SF brick building, and approximately 1,300 linear feet of concrete wall. The work
Read More -
April 4, 2022 – Demolition Update
The demolition contractor continues to make good progress taking down the buildings at 3200 S. Kedzie. There have been over 200 loads of scrap and construction & demo debris removed from the site
Read More -
March 28, 2022 – Demolition Update
Demolition work is progressing and on-schedule at the former Azteca Mall property. The buildings continue to be taken down, the materials are being sorted and hauled off-site for disposal. There are
Read More -
March 21, 2022 – Demolition Update
Demolition work resumed at the former Azteca Mall property this past week. The buildings are being taken down to grade, and materials are being sorted and taken off-site for proper disposal. Air
Read More -
March 14, 2022 – Demolition Update
CSDC hosted a virtual community meeting on March 9th at 6 PM and provided updates on the demolition project to date, and the plans going forward. The presentation for that meeting can be found under
Read More -
March 7, 2022 – Demolition Update
The City of Chicago issued the demolition permit for the second phase of work, which will begin on March 14th. Chicago Southwest Development Corporation invites you to join its third Demolition
Read More -
February 28, 2022- Demolition Update
Demolition work and air quality testing is paused until the demolition permit for the Azteca Mall parcel is received from the City of
Read More -
February 21, 2022- Demolition Update
There was no demolition work completed this past week and none scheduled for this week. Demolition work and air quality testing is paused until the demolition permit for the Azteca Mall parcel is
Read More -
February 14, 2022 – Demolition Update
As of Friday February 11th demolition work on the western portion of the property was substantially completed. Demolition work and testing is paused until the Demolition Permit for the Azteca Mall